Dr
Detlef Reschke
(DESY), Dr
Waldemar Singer
(DESY)
23/04/2015, 14:00
Cavity production will come to an end in fall 2015 and testing should be finished after the last retreatment of some cavities. We assume the testing will be finished end of 2015.
Dr
Walid kaabi
(LAL),
Wolf-Dietrich Möller
(DESY)
23/04/2015, 14:30
Power coupler production runs at a rate of 8 per week from Thales. From 4/2015 on we are going to receive additional 4 couplers per week from CPI. An overview will be given about the production and the testing at LAL (incl. the outlook to the CPI coupler conditioning).
Lutz Lilje
(DESY -MVS-)
23/04/2015, 15:00
Status of all cold vacuum components incl. number / production rate (matching the needs for an accelerated module assembly). Experience with the L1 installation will be given elsewhere (L1 Installation Session).
Dr
Jacek Sekutowicz
(DESY)
23/04/2015, 15:15
Status of the component production should be given. Emphasis should be on the availavility of absorbers for the linac installation.
Dr
Fernando Toral
(CIEMAT), Dr
Heiner Brueck
(DESY, MKS)
23/04/2015, 15:30
The successful finishing of the cold magnets should be reported with some concluding remarks.
Claire Simon
(CEA Saclay), Dr
Dirk Nölle
(DESY, MDI)
23/04/2015, 15:45
Availabiity of cold BPMs for BQU integration
Mr
Axel matheisen
(DESY), Mr
Kay Jensch
(DESY), Dr
Olivier Napoly
(CEA-Saclay), Mr
Stéphane BERRY
(CEA-Saclay)
23/04/2015, 16:30
Challenges in string & module assembly should be presented and discussed; inclduing BQU assembly.
Dr
Elmar Vogel
(DESY), Mr
Jacek Swierblewski
(MKS 1),
Lutz Lilje
(DESY -MVS-), Dr
Olivier Napoly
(CEA-Saclay),
Wolf-Dietrich Möller
(DESY)
23/04/2015, 17:15
Major non-conformities; solved issues and still ongoing challenges; emphasis on components and modules
Dr
Elmar Vogel
(DESY),
Hans Weise
(DESY), Mr
Kay Jensch
(DESY),
Lutz Lilje
(DESY -MVS-), Dr
Olivier Napoly
(CEA-Saclay),
Wolf-Dietrich Möller
(DESY), Mr
axel matheisen
(DESY)
23/04/2015, 18:00
discussion of some first ideas wrt. possible module repair work should be collected; which infrastructure could be used when by whom to repair modules?