TCM 06-2007
Tuesday 19 June 2007 -
09:00
Monday 18 June 2007
Tuesday 19 June 2007
09:00
Beam Lines & Components Naming Convention
-
Thomas Hott
Beam Lines & Components Naming Convention
Thomas Hott
09:00 - 09:10
09:15
Review procedures for XFEL
-
Thomas Hott
Review procedures for XFEL
Thomas Hott
09:15 - 09:25
09:30
XTL Design -> Update
-
Thomas Hott
XTL Design -> Update
Thomas Hott
09:30 - 09:45
09:50
Fire detection and fire fighting underneath XTL floor slabs
-
Jochen May
Fire detection and fire fighting underneath XTL floor slabs
Jochen May
09:50 - 10:00
10:05
Bunch Compressors -> Base line layout + status of design effort
-
Christopher Gerth
Bunch Compressors -> Base line layout + status of design effort
Christopher Gerth
10:05 - 10:20
10:25
CAD tools for cable routing -> Update
-
Thorsten Stoye
CAD tools for cable routing -> Update
Thorsten Stoye
10:25 - 10:35
10:40
Mock-Up -> Update on status, next steps & safety procedures
-
Norbert Meyners
Mock-Up -> Update on status, next steps & safety procedures
Norbert Meyners
10:40 - 10:55