The injector complex (underground) has been handed over. There are some remaining tasks (floors in XTIN floor 6&7 and XHEIN). Installation of main water pipes in XTIN shaft has started. Installation of cable trays in XSE shaft on hold due to missing safety assessment.
First part of support construction for pulse transformers in XTIN UG3 in place, alignment problematic (date for discussion?). Special topic session on friday 11:30h 24/200 concerning rack space and rack occupation.
New layout of walkway behind beamline. Comments from work packages not complete (cryo).