JETI40@HH Meeting

Europe/Berlin

Minutes Feburary 14th:

  • Grigory presented his studies on the laser beam-line in the building. The main conclusion is that the laser must come on the same plane as the electron beam line if one want to use a coupled mirror mount for the transport.
  • He also explored alternative location (eg in the surface building on the first floor). However, the transport to such a location would be very complicated:
    • Either need to go through the crane shaft.
    • Or need to drill the radiation shiedling (2m thick with 45 degrees angle).
    • disfavoured.
  • Maik presented the curves of the temperature and humidity readins since 2012.
    • The system in Jena was able to operate with a temperature stabilisation of about 22+-1 degrees. 
    • The dispertion of the humidity is much larger but they were using some settings for summer and winter.
    • Cover dust, and AC should be stabilized aorund the laser area (specs in the twiki).
    • Conclusion that such a system could be done in HERA West for approx 50k.
    • Crane can lift up 1 ton.
    • No restriction to come from the top.
  • Alex and Falk will come in Hamburg on March 3rd evening and on the 4th, they will live at 16h00 that day.
  • Need to converge on a new timeslot for the meeting, mornings dont work very well for Karsten.